The footers were
then formed with a new product called Form-a-Drain by Certainteed. This material is
plastic, has the shape of a 2X6, but is permanently left as part of the footer. The
form is hollow and has slits that face inside the house and to the exterior. These
slits allow the product to act as a drain for water on the outside of the house and on the
inside it becomes a part of the radon abatement system.
Next, rebar
was placed in the forms and then they were filled with concrete. All of the rebar
used in our footers came to us as scrap left over from the new ASU Convocation Center in
Boone. Since it was specified for a very large building, it was three to five
times larger than required for our job, but ended up costing one tenth the price of new
rebar.
The
footers form the base for the outside walls which are made of ICF blocks (Insulated
Concrete Forms). This form was also filled with concrete to form a permanent
structure. Use of this material was chosen because of its simplicity and ease in
construction and also because the finished product would be a stucture of superior quality
and efficiency. Walls using ICFs have a working insulation efficiency comparable to
a stick built home with R50 outside walls. We chose to use the award winning IntegraSpec® form
produced by Phil Insul Corporation of Kitchner, Ontario.
We found this product far superior to any other product available in the
marketplace. See our Sponsors Page for more information.
The
first construction on outside walls began with the building of a foundation wall on the
descending slope side of the home. It created a level plane to meet the other
footers. This gave us an even level for pouring the next floor. This wall was
9 feet high and ran 54 feet in back and another 35 feet on the side of the house.
Once that was
complete, we were able to begin building the basement walls. The back wall was set
to face 190 degrees for maximum sun exposure. We built the frames for the six
windows and two doors on that wall. This would form our basement solar collection
area.
We
decided to add a large garage door in the basement to allow us to more easily move
materials, bikes, equipment, and furniture in and out of the house. It also provided
us with an access for a tractor during construction.
Slowly we
completed this final basement wall. We worked on this part through February 2002,
celebrating our first anniversary since starting the house. We were fortunate that
we did not have a lot of snow to deal with and the weather remained somewhat mild.
This was unlike our experience in prior years in the rugged Appalachian Mountains.
As of
the end of February, we completed the final wall. The last steps before filling
these walls with concrete, will be to mount the supports for the main floor trusses and
set the large steel beams seen below laying in the basement.
Erection
of walkboards, bracing, and setting of scaffolding was done to allow the concrete
pumping crew to move around on the inside of the perimeter wall. Once this wall is set,
bracing and scaffolding was removed and used to support the first floor walls.
From the back
of the house we will be able to walk out at ground level
on the eastern side and a deck will circle that level to allow exit from the western door.